RATE ANALYSIS FOR Power Cables |
|
|
|
|
|
|
|
|
|
|
CONSTRUCTION OF PASSENGER TERMINAL BUILDING AND ALLIED
ELECTRICAL & MECHANICAL WORKS AT
INTERNATIONAL AIRPORT -
(PACKAGE -6) |
|
|
|
|
|
|
|
|
|
|
|
4 CORE 150 mm² |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measuring Unit |
|
|
|
|
Ru.Meter |
|
|
|
|
|
|
|
|
|
|
|
|
|
Item Desc. |
Supply at
site, laying connecting, testing and commissioning of Cu/Pvc/Pvc
600 /100V BS:6346 4 core 150mm² cable (Pakistan Cable) Pad Mounted Transformer No. 3 to ATC
Tower pelaid in conduit/ trench or on
cable tray. Actual length of cable to be installed shall be practically
measured at site |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
A |
Materials: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. |
Cu/Pvc/Pvc 600 /100V
BS:6346 4 core 150mm² cable |
|
|
|
|
|
|
|
|
= |
5,475.00 Rs./Mtr |
|
|
|
|
|
|
GST 17% of |
= |
5,475.00 x 17% = 930.75 Rs./Mtr. |
|
|
|
|
|
|
Rate per Mtr |
= |
5,475.00+ 930.75
=6,405.75 |
|
|
|
|
|
|
Cu/Pvc/Pvc 600 /100V 4 core 150mm² cable |
= |
1 Mtr @ 6,405.75Rs. / Mtr. |
|
= |
6,405.75 |
Rs./ Mtr. |
|
2. |
Maintenance charges for
replacement/ repairing |
|
|
|
|
|
|
during defects liability
period |
= |
10% |
|
= |
640.58 |
Rs./ Mtr. |
|
3. |
Store Handling Charges
incl unloading |
= |
2% |
|
= |
128.12 |
Rs./ Mtr. |
|
4. |
Wastage |
= |
5% |
|
= |
320.29 |
Rs./ Mtr. |
|
5. |
Carridge from Market |
= |
5% |
|
= |
- |
Rs./ Mtr. |
|
|
|
|
|
|
Sub Total Cost A: |
= |
7,494.73 |
Rs. / Mtr. |
|
B |
Equipments: |
|
|
|
|
|
|
|
1. |
T & P of ( A1.) |
= |
1% |
|
= |
64.06 |
Rs./ Mtr. |
|
|
|
|
|
|
Sub Total Cost B: |
= |
64.06 |
Rs. / Mtr. |
|
C |
Manpower : |
|
|
|
|
|
|
|
1. |
Foreman/Supervisor |
= |
1 Hr/ Mtr @ 121.15
Rs./ Hr |
|
= |
121.15 |
Rs./ Mtr. |
|
2. |
Electrician |
= |
2 Hr/ Mtr. @ 80.77
Rs./ Hr |
|
= |
161.54 |
Rs./ Mtr. |
|
3. |
Electrician Helper |
|
2 Hr/ No @ 47.12 Rs./
Hr |
|
= |
94.24 |
Rs. / Mtr. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sub Total Cost C: |
= |
376.93 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
D |
Total Cost (A+B+C) |
|
|
|
= |
7,935.72 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
E |
Add 0.5 % Water Charges |
|
|
|
= |
39.68 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
F |
Add 2% Testing &
Commissioning Charges (D+E)x 2% |
|
= |
159.51 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
G |
Total Cost (D+E+F) |
|
|
|
= |
8,134.90 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
H |
Overheads (In-direct
Cost) 25 % |
|
|
|
= |
2,034.00 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
I |
Grand Total
Cost (G+H) |
|
|
|
= |
10,168.90 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
J |
Contractor Profit 10
% |
|
|
|
= |
1,017.00 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
K |
Add Income Tax 6% |
|
|
|
= |
714.10 |
Rs./ Mtr. |
|
|
|
|
|
|
|
|
|
|
|
L |
Net Cost for Supply at site, laying connecting, testing and
commissioning of Cu/Pvc/Pvc 600 /100V BS:6346 4 core 150mm² cable (Pakistan Cable) Pad Mounted Transformer No. 3 to ATC
Tower pelaid in conduit/ trench or on
cable tray. Actual length of cable to be installed shall be practically
measured at site. (L = I+J+K) |
11,900.00 |
Rs./
Mtr. |